Bond Project Updates
October 2024
September 2024
August 2024
July 2024
May 2024
April 2024
The Board approved the contract for the Access Control Security System to 3Sixty Integrated at a total cost of $1,334,526. Funding for this project will be provided from 2023 Bond funds. This system is part of the district-wide plan to outfit the District's campus sites with the best possible security solutions.
March 2024
February 2024
January 2024
November 2023
The Board approved the Schematic Design drawings that were presented by RVK Architecture. The budget for this project is approximately 18,000,000. The cost of this project will be funded by 2023 Bond funds.
Construction Delivery Method for the New Elementary #12 Project
The Board approved the Construction Manager at Risk method as the delivery method for Southwest ISD Elementary #12 project. The District, along with Marmon Mok, believe that the Construction Manager at Risk delivery method will provide the best value for the District. This method is based on the selected General Contractor being an active with the architect throughout the planning and design phase. The estimated budget for this project is approximately $39,900,000 and will be funded by the 2023 Bond.
Construction Delivery Method for the Kriewald Road School of the Arts Renovation Project
The Board approved the Construction Manager at Risk method as the delivery method for Kriewald Road School of the Arts Renovation project.The District, along with Huckabee, believe that the Construction Manager at Risk delivery method will provide the best value for the District. This method is based on the selected General Contractor being an active participant with the Architect throughout the planning and design phase. The estimated budget for this project is approximately $18,000,000 and will be funded by the 2023 Bond.
October 2023
September 2023
Construction Manager at Risk Contract for the New Central Administration Building Project
The Board approved Kencon Constructors, LLC as the Construction Manager at Risk for the New Central Administration Building project. The contract for this undertaking amounts to $865,000.00 and will be funded through the bond. Bids for the CMAR contract were solicited on August 29, 2023, resulting in the receipt of 10 bids. These bids encompassed costs for both the pre-construction and construction phases, spanning a range from $665,204.00 to $2,745,298.00. District Staff and RVK Architecture meticulously evaluated and ranked the bidding firms based on the selection criteria published in the solicitation. Out of the 10 submitted bids, Kencon Constructors was the highest-scoring firm.
Schematic Design Drawings for the SWHS Stadium Press Box Renovation
The Board has granted approval for the Schematic Design drawings, which were conceived and presented by Pfluger Architects. In a collaborative effort, District staff and Pfluger Architects identified the program and design requirements for the SWHS Stadium Press Box Renovation project. The project is allocated a budget of approximately $5,500,000, and funding for it will be derived from the 2023 Bond funds.
July 2023
Architectural Firms for the 2023 Bond Projects Initial Bond Sale
The Board approved the firms listed below to provide architectural services for the 2023 Bond Projects' initial bond sale. District staff is now prepared to start the architectural programming phase for several of these projects. This decision follows Southwest ISD voters' approval of a $250 million bond on May 6, 2023. The bond aims to facilitate the construction of two new elementary schools, establish a new central administration and professional development center, implement safety upgrades across all campuses, and renovate or expand multiple other campuses district-wide. It is important to note that all selected firms are part of the pre-approved Architectural Services from RFQ 2223-111.